3.1.2.2 Machine, Boiler, and Steam Boiler

Details
No. List of Laws Laws
7 Issues of Factory Act B.E. 2535
3 Issues of The Enhancement And Conservation Of National Environmental Quality Act B.E. 2535
1 The factory business entrepreneur for producing, modifying, or building boiler or steam boiler using fluid as heat medium or container supporting the pressure, shall provide for design of production, and the examination of production shall be supported by user’s manual, and the maintenance and preparation for report on production, examination, and safety test of product shall be under criteria and method as published in the Government Gazette. [2],[3]
2 The factory business entrepreneur for producing, modifying, or building boiler or steam boiler using fluid as heat medium or container supporting the pressure, shall install equipment that is desgined produced, and examined from manufacturer’s factory, both domestic production and foreign production, under the criteria and method published in the Government Gazette. [2],[3]
3 Boiler and steam boiler that uses fluid as heat medium or container supporting pressure shall have safety equipment, installation site; the installation, examinatoion and test after installation and piping system shall be designed, calculated,and controlled to be under engineering standard under criteria and method as published in the Government Gazette. [2],[3]
4 Factory that uses boiler shall install equipment or tool used in treatment or adjusting water condition in boiler system or adjusting water condition into boiler so that the property of water would be under standard, and shall prepare for report on the information of installation, examinat, and test after installation and moving under criteria and method as published in the Government Gazette. [2],[3]
5 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall send report on result of safety test to the Department of Industiral Works within 30 days as from the day when examination is performed or test under criteria and method as published in the Government Gazette. [2],[3]
6 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall send report on result of repair, modification, and result of examination and test after repair and modification to the Department of Industrial Works first before use, under criteria and method as published in the Government Gazette. [2],[3]
7 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall follow criteria and method as published in the Government Gazette. [2],[3]
8 The controller of boiler or steam boiler that uses fluie ad heat medium, the engineer controlling and directing the use of boiler, the engineer who controls the construction or repair of boiler or steam boiler that uses fluid as heat medium, the engineer who examines and tests the boiler or steam boiler that uses fluid as heat medium, engineering certification unit on part of boiler or steam boiler that uses fluid as heat medium, shall have qualifications and duty and responsibility as specified by the Department of Industrial Works and shall be registered with the Department of Industrial Works under criteria and method as specified by the Department of Industrial Works. [2],[4]
9 The training on the course and the standard examination nof the controller at the boiler or steam boiler that uses fluid as heat medium shall be under criteria and method as specified by the Department of Industrial Works. [2],[4]
10 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium shall provide for design and calculation of boiler or steam boiler using fluid as heat medium to be constructed under the TIS or international standard including ASME standard, JIS, EN or equivalent, and shall provide for engineering certification unit on part of boiler or steam boiler that uses fluid as heat medium, or the engineer who controls the construction or repair of boiler or steam boiler using fluid as heat medium, to check and certify form and collect form and certificate in the factory so that the official can examine. [2],[4]
11 The factory business entrepreneur who constructs boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall prepare for Manufacturing Data Report and send the report of design certification nand report on the examination of construction to the Department of Industiral works, this shall be under criteria and method as pecified by the Department of Industrial Works. [2],[4]
12 The factory business entrepreneur who uses boiler shall provide for examination of boiler by the engineer whose duty is to examine or test, or the engineering certification unit on boiler or steam boiler using fluid as heat medium for at least once a year under criteria and method as pecified by the Department of Industrial Works. [2],[4]
13 The factory business entrepreneur who uses boiler that uses fluid as heat medium shall provide for examination and test of safety during use by the engineer whose duty is to examine and test, or the engineering certification unit on boiler or steam boiler using fluid as heat medium for at least once a year under criteria and method as pecified by the Department of Industrial Works. [2],[4]
14 Boiler or steam boiler using fluid as heat medium, that has not been used fo 6 consecutively months, if it is to be used again, the factory business entrepreneur shall examine first under criteria and method as pecified by the Department of Industrial Works. [2],[4]
15 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium, who intends to repair or modify boiler or steam boiler using fluid as heat medium on the part that affects the structure supporting pressure, shall take action under criteria and method as pecified by the Department of Industrial Works, and shall send the report of result of the modification and report to the Department of Industrial Works within 30 days after repair and modification; this shall be under report form as specified by the Department of Industrial Works. [2],[4]
16 For the cancellation of use of boiler or steam boiler using fluid as heat medium to be moved or destroyed, the factory business entrepreneur shall inform the Department of Industrial Wroks first before moving or destroying for not less than 30 working days. [2],[4]
17 The factory business entrepreneur who uses boiler shall adjust water condition for boiler to be udnre safety measure concerned with boiler or steam boiler using fluid as heat medium or container supporting the pressure as specified by the factory. [2],[5]
18 Safety sytem or equipment and the installation shall be under the specification on standard boiler or steam boiler using fluid as heat medium or safety measure concerned in case when there is no any standard specifying the use of equipment or safety system and the installation under engineering principle in case when the equipment or safety system or the installation is not under the Ministry of Industry’s Announcement, the factory business entrepreneur shall be granted with approval from the Department of Industrial Works first before performing any operation. [2],[6]
19 The factory business entrepreneur who uses boiler with 20 tons or over per hour per boiler who intends to request for approval in examining within boiler for every more than 1 year or not more than 5 years per time, shall take action under criteria and method as pecified by the Department of Industrial Works. [2],[10]
20 The factory business entrepreneur who intends to apply for approval in examining within boiler every period of more than 1 year but not exceeding 5 years per time, shall submit the application to the Safety Technology Office of the Department of Industrial Works under Form of sorPor. 1-26. [2],[10]
21 The factory business entrepreneur who is granted an approval in examining within boiler every period of more than 1 year but not exceeding 5 years per time, shall prepare for report and send it to the Safety Technology Office of the Department of Industrial Works for at least once a year. [2],[10]
22 The law specifies that the business place that uses steam boiler which is the source of pollution, shall be controlled in releasing waste air into the atmosphere, and specifieds the opacity standard of smoke released from the business place that uses steam boiler, by examination, calculaton, comparision, and conclusion on the result of the examination into opacity to be as published by the Pollution Control Committee in the Government Gazette. [1],[8],[9]
23 The law specifies the smoke emission that is contaminated in the air that is released from chimney of boiler of the factory, is the air released from chimney of the boiler of third-type factory with the production capacity of 1 tons or over per hour, must have smoke that would cause opacity when checking by ringelmann smoke chart of not more than 10 % in the opacity examination while the factory business is running and the boiler is functioning normally; the method of examination, calculation, comparison, and conclusion of the opacity examination shall be done by using method as approved by the Department of Industrial Works. [2],[7]
Details
No. List of Laws Laws
7 Issues of Factory Act B.E. 2535
3 Issues of The Enhancement And Conservation Of National Environmental Quality Act B.E. 2535
1 The factory business entrepreneur for producing, modifying, or building boiler or steam boiler using fluid as heat medium or container supporting the pressure, shall provide for design of production, and the examination of production shall be supported by user’s manual, and the maintenance and preparation for report on production, examination, and safety test of product shall be under criteria and method as published in the Government Gazette. [2],[3]
2 The factory business entrepreneur for producing, modifying, or building boiler or steam boiler using fluid as heat medium or container supporting the pressure, shall install equipment that is desgined produced, and examined from manufacturer’s factory, both domestic production and foreign production, under the criteria and method published in the Government Gazette. [2],[3]
3 Boiler and steam boiler that uses fluid as heat medium or container supporting pressure shall have safety equipment, installation site; the installation, examinatoion and test after installation and piping system shall be designed, calculated,and controlled to be under engineering standard under criteria and method as published in the Government Gazette. [2],[3]
4 Factory that uses boiler shall install equipment or tool used in treatment or adjusting water condition in boiler system or adjusting water condition into boiler so that the property of water would be under standard, and shall prepare for report on the information of installation, examinat, and test after installation and moving under criteria and method as published in the Government Gazette. [2],[3]
5 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall send report on result of safety test to the Department of Industiral Works within 30 days as from the day when examination is performed or test under criteria and method as published in the Government Gazette. [2],[3]
6 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall send report on result of repair, modification, and result of examination and test after repair and modification to the Department of Industrial Works first before use, under criteria and method as published in the Government Gazette. [2],[3]
7 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall follow criteria and method as published in the Government Gazette. [2],[3]
8 The controller of boiler or steam boiler that uses fluie ad heat medium, the engineer controlling and directing the use of boiler, the engineer who controls the construction or repair of boiler or steam boiler that uses fluid as heat medium, the engineer who examines and tests the boiler or steam boiler that uses fluid as heat medium, engineering certification unit on part of boiler or steam boiler that uses fluid as heat medium, shall have qualifications and duty and responsibility as specified by the Department of Industrial Works and shall be registered with the Department of Industrial Works under criteria and method as specified by the Department of Industrial Works. [2],[4]
9 The training on the course and the standard examination nof the controller at the boiler or steam boiler that uses fluid as heat medium shall be under criteria and method as specified by the Department of Industrial Works. [2],[4]
10 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium shall provide for design and calculation of boiler or steam boiler using fluid as heat medium to be constructed under the TIS or international standard including ASME standard, JIS, EN or equivalent, and shall provide for engineering certification unit on part of boiler or steam boiler that uses fluid as heat medium, or the engineer who controls the construction or repair of boiler or steam boiler using fluid as heat medium, to check and certify form and collect form and certificate in the factory so that the official can examine. [2],[4]
11 The factory business entrepreneur who constructs boiler or steam boiler using fluid as heat medium or container supporting the pressuse, shall prepare for Manufacturing Data Report and send the report of design certification nand report on the examination of construction to the Department of Industiral works, this shall be under criteria and method as pecified by the Department of Industrial Works. [2],[4]
12 The factory business entrepreneur who uses boiler shall provide for examination of boiler by the engineer whose duty is to examine or test, or the engineering certification unit on boiler or steam boiler using fluid as heat medium for at least once a year under criteria and method as pecified by the Department of Industrial Works. [2],[4]
13 The factory business entrepreneur who uses boiler that uses fluid as heat medium shall provide for examination and test of safety during use by the engineer whose duty is to examine and test, or the engineering certification unit on boiler or steam boiler using fluid as heat medium for at least once a year under criteria and method as pecified by the Department of Industrial Works. [2],[4]
14 Boiler or steam boiler using fluid as heat medium, that has not been used fo 6 consecutively months, if it is to be used again, the factory business entrepreneur shall examine first under criteria and method as pecified by the Department of Industrial Works. [2],[4]
15 The factory business entrepreneur who uses boiler or steam boiler using fluid as heat medium, who intends to repair or modify boiler or steam boiler using fluid as heat medium on the part that affects the structure supporting pressure, shall take action under criteria and method as pecified by the Department of Industrial Works, and shall send the report of result of the modification and report to the Department of Industrial Works within 30 days after repair and modification; this shall be under report form as specified by the Department of Industrial Works. [2],[4]
16 For the cancellation of use of boiler or steam boiler using fluid as heat medium to be moved or destroyed, the factory business entrepreneur shall inform the Department of Industrial Wroks first before moving or destroying for not less than 30 working days. [2],[4]
17 The factory business entrepreneur who uses boiler shall adjust water condition for boiler to be udnre safety measure concerned with boiler or steam boiler using fluid as heat medium or container supporting the pressure as specified by the factory. [2],[5]
18 Safety sytem or equipment and the installation shall be under the specification on standard boiler or steam boiler using fluid as heat medium or safety measure concerned in case when there is no any standard specifying the use of equipment or safety system and the installation under engineering principle in case when the equipment or safety system or the installation is not under the Ministry of Industry’s Announcement, the factory business entrepreneur shall be granted with approval from the Department of Industrial Works first before performing any operation. [2],[6]
19 The factory business entrepreneur who uses boiler with 20 tons or over per hour per boiler who intends to request for approval in examining within boiler for every more than 1 year or not more than 5 years per time, shall take action under criteria and method as pecified by the Department of Industrial Works. [2],[10]
20 The factory business entrepreneur who intends to apply for approval in examining within boiler every period of more than 1 year but not exceeding 5 years per time, shall submit the application to the Safety Technology Office of the Department of Industrial Works under Form of sorPor. 1-26. [2],[10]
21 The factory business entrepreneur who is granted an approval in examining within boiler every period of more than 1 year but not exceeding 5 years per time, shall prepare for report and send it to the Safety Technology Office of the Department of Industrial Works for at least once a year. [2],[10]
22 The law specifies that the business place that uses steam boiler which is the source of pollution, shall be controlled in releasing waste air into the atmosphere, and specifieds the opacity standard of smoke released from the business place that uses steam boiler, by examination, calculaton, comparision, and conclusion on the result of the examination into opacity to be as published by the Pollution Control Committee in the Government Gazette. [1],[8],[9]
23 The law specifies the smoke emission that is contaminated in the air that is released from chimney of boiler of the factory, is the air released from chimney of the boiler of third-type factory with the production capacity of 1 tons or over per hour, must have smoke that would cause opacity when checking by ringelmann smoke chart of not more than 10 % in the opacity examination while the factory business is running and the boiler is functioning normally; the method of examination, calculation, comparison, and conclusion of the opacity examination shall be done by using method as approved by the Department of Industrial Works. [2],[7]
Relavant Laws
No. List of Laws Laws
1 The Enhancement And Conservation Of National Environmental Quality Act, B.E.2535 (1992)
2 Factory Act, B.E.2535 (1992)
3 Regulations Of The Ministry Of Industry: The Security Measures Of Steamer, Boiler Using Liquid As Heat Carrier, And Pressured Vessel In A Factory, B.E.2549 (2006)
4 Notification Of Ministry Of Industry: The Safety Measures For A Boiler And Boiler Using Liquid As Heat Carrier, B.E.2549 (2006)
5 Notification Of Ministry Of Industry: The Water Properties For A Boiler, B.E.2549 (2006)
6 Notification Of Ministry Of Industry: The Safety Equipment For A Boiler And Boiler Using Liquid As Heat Carrier, B.E.2549 (2006)
7 Notification Of Ministry Of Industry: The Opacity Of Smoke Emitted From A Stack Of Boiler From A Factory, B.E.2549 (2006)
8 Notification Of The Ministry Of Natural Resources And Environment: The Business Which Uses A Boiler, As A Source Of Pollution, The Emission Must Be Controlled Before Releasing To The Atmosphere
9 Notification Of The Ministry Of Natural Resources And Environment: The Smoke Opacity Emission Standard For A Boiler
10 Notification Of Department Of Industrial Works: The Criteria And Method For Approval Of Internal Boiler Audit In Every Period More Than 1 Year, But Not Exceed 5 Year Of Inspection, B.E.2555 (2012)
Forms
No. List of Forms Forms
1 The application of consent for inspecting the inner of boiler which the time period exceeds 1 year but not over 5 years per 1 inspection (the form of Sor Por 1-26)
2 The agreement paper of inspecting the inner of boiler in the period of time which exceeds 1 year but not over 5 years per one inspection (the form of Sor Por 1-27)
3 The report of inspecting the outer of boiler and the operation of control system and safety equipment (the form of Sor Phor 1-28)