2.2 Preparation of EIA/EHIA/IEE Report

Details
1. Preparing for EIA / EHIA’s report
The entrepreneur shall check the code of industrial factory, shall check that the types of business conducted requires to have the Environmental Impact Assessment (EIA) or the EIA for the project or business that may cause serious impact on the community in terms of environmental health impact assessment (EHIA). In preparing for these 2 kinds of report, it depends on the types of the Project divided into 4 cases:
• In case of the project or business that must be given permission from the government agency and the project or business which does not have to be given approval from the cabinet
• In case of the project or business of the government sector, state enterprise, or the joint project with the private sector, that must presented to the cabinet for approval
• In case of the project or business that may cause serious impact on the community, for the project or business that must be given permission from the government, and the project or business that does not have to receive approval from the cabinet
• In case of the project or the business that may cause serious impact on the community in EHIA, in case of the project or In case of the project or business of the government sector, state enterprise, or the joint project with the private sector, that must presented to the cabinet for approval
2. IEE Preparing for IEE’s report
In preparing for Initial Environmental Examination Report (IEE), there shall be operation in case of the establishment of factory in the control area that is announced as the type of industry in the Attachment of specific law where there shall be the report, or in case of the area on which the Industrial Estate is to be located specifies that it is the area where the industrial factory shall prepare for Initial Environmental Examination Report, or is the industry that may spread pollution such as dangerous industrial waste recycling factory or factory with burning process. On some occasion, the submission for privileges of investment may need the IEE’s report in order for consideration by the authorized staff.
ขั้นตอนการจัดทำรายงาน EIA
ขั้นตอนการจัดทำรายงาน EHIA
ขั้นตอนการจัดทำรายงาน IEE
Details
1. Preparing for EIA / EHIA’s report
The entrepreneur shall check the code of industrial factory, shall check that the types of business conducted requires to have the Environmental Impact Assessment (EIA) or the EIA for the project or business that may cause serious impact on the community in terms of environmental health impact assessment (EHIA). In preparing for these 2 kinds of report, it depends on the types of the Project divided into 4 cases:
• In case of the project or business that must be given permission from the government agency and the project or business which does not have to be given approval from the cabinet
• In case of the project or business of the government sector, state enterprise, or the joint project with the private sector, that must presented to the cabinet for approval
• In case of the project or business that may cause serious impact on the community, for the project or business that must be given permission from the government, and the project or business that does not have to receive approval from the cabinet
• In case of the project or the business that may cause serious impact on the community in EHIA, in case of the project or In case of the project or business of the government sector, state enterprise, or the joint project with the private sector, that must presented to the cabinet for approval
2. IEE Preparing for IEE’s report
In preparing for Initial Environmental Examination Report (IEE), there shall be operation in case of the establishment of factory in the control area that is announced as the type of industry in the Attachment of specific law where there shall be the report, or in case of the area on which the Industrial Estate is to be located specifies that it is the area where the industrial factory shall prepare for Initial Environmental Examination Report, or is the industry that may spread pollution such as dangerous industrial waste recycling factory or factory with burning process. On some occasion, the submission for privileges of investment may need the IEE’s report in order for consideration by the authorized staff.
Relavant Laws
No. List of Laws Laws
1 The Enhancement And Conservation Of National Environmental Quality Act, B.E.2535 (1992)
2 Industrial Estate Authority Of Thailand Act, B.E.2522 (1979)
3 Industrial Estate Authority Of Thailand Act (No.2), B.E.2534 (1991)
4 Industrial Estate Authority Of Thailand Act (No.3), B.E.2539 (1996)
5 Industrial Estate Authority Of Thailand Act (No.4), B.E.2550 (2007)
6 Factory Act, B.E.2535 (1992)
7 The Enhancement And Conservation Of National Environmental Quality Act, B.E.2535 (1992)
8 Notification Of Ministry Of Natural Resources And Environment: Type, Size And Practice Method For Government's And Private Sector's Projects Or Businesses Which Cause Severely Community Effects On The Environment, Natural Resources And Health, Must Compile An Environmental Impact Assessment Report B.E.2553 (2010)
9 Notification Of Ministry Of Natural Resources And Environment: Type, Size And Practice Method For Government's And Private Sector's Projects Or Businesses Which Cause Severely Community Effects On The Environment, Natural Resources And Health, Must Compile An Environmental Impact Assessment Report No.2 B.E.2553 (2010)
10 Notification Of Ministry Of Natural Resources And Environment: Type, Size And Practice Method For Government's And Private Sector's Projects Or Businesses Which Cause Severely Community Effects In Environment, Natural Resources And Health, Must Compile An Environmental Impact Assessment Report (No.4) B.E.2559 (2016)
11 Notification Of Ministry Of Natural Resources And Environment: The Specification On Type And Size Of Project Or Activity And The Criteria, Method Of Project Or Activities May Request The Exemption For Preparation Of Environmental Impact Assessment Report
12 Notification Of Ministry Of Natural Resources And Environment: Type And Size Of Projects Or Businesses Which Are Required To Prepare The Environmental Impact Assessment Report And Criteria, Method, Procedure And Guidelines Of Compiling An Environmental Impact Assessment Report
13 Notification Of Ministry Of Natural Resources And Environment: Type And Size Of Projects Or Businesses Which Are Required To Prepare The Environmental Impact Assessment Report And Criteria, Method, Procedure And Guidelines Of Compiling An Environmental Impact Assessment Report No.5, B.E.2557 (2014)
14 Notification Of Ministry Of Natural Resources And Environment: Type And Size Of Projects Or Businesses Which Are Required To Prepare The Environmental Impact Assessment Report And Criteria, Method, Procedure And Guidelines Of Compiling An Environmental Impact Assessment Report No.6, B.E.2557 (2014)
15 Notification Of Ministry Of Natural Resources And Environment: Type And Size Of Projects Or Businesses Which Are Required To Prepare The Environmental Impact Assessment Report And Criteria, Method, Procedure And Guidelines Of Compiling An Environmental Impact Assessment Report (No.8), B.E.2558 (2015)
16 Notification Of Ministry Of Natural Resources And Environment: The Criteria, Procedure, Regulations And Method Of Compiling An Environmental Impact Assessment Report For Projects Or Businesses Which Might Cause Severely Community Effects On The Environment, Natural Resources And Heath
17 Notification Of Ministry Of Natural Resources And Environment: The Criteria, Procedure, Regulations And Method Of Compiling An Environmental Impact Assessment Report For Projects Or Businesses Which Might Cause Severely Community Effect On The Environment, Natural Resources And Heath No.2 B.E.2553 (2010)
18 Notification Of Ministry Of Natural Resources And Environment: The Specification On Criteria, Method, Procedure And Guidelines For Compilation Of Environmental Impact Assessment Report For The Projects Or Activities That May Affect Community Severely Both In The Quality Of Environment, Natural Resources And Health (No.3), B.E.2555 (2012)
19 Notification Of The Ministry Of Science, Technology And Environment: The Specification On Type And Size Of Projects Or Activities Of Government Agency, State Enterprise Or Private Sector May Prepare An Environmental Impact Assessment Report
20 Notification Of The Ministry Of Science, Technology And Environment: Defining Type And Size For Projects Or Activities Of Government Agency, State Enterprise Or Private Sector Must Prepare An Environmental Impact Assessment Report No.2, B.E.2535 (1992)
21 Notification Of The Ministry Of Science, Technology And Environment: The Specification On Criteria, Method, Procedure And Guidelines For Preparation An Environmental Impact Assessment Report
22 Notification Of The Ministry Of Science, Technology And Environment: The Specification On Criteria, Method, Procedure And Guidelines For Preparation Of Environmental Impact Assessment Report No.2, B.E.2535 (1992)
23 Notification Of The Ministry Of Science, Technology And Environment: The Specification On Criteria, Method, Procedure And Guideline For Preparation Of Environmental Impact Assessment Report No.3, B.E.2539 (1996)
24 Notification Of The Ministry Of Science, Technology And Environment: Defining Type And Size For Projects Or Activities Of Government Agency, State Enterprise Or Private Sector Must Prepare An Environmental Impact Assessment Report No.3, B.E.2539 (1996)
25 Notification Of National Environment Board No.1, B.E.2555 (2012): The Criteria And Method Of Appointment Specialist Committee Member In Considering An Environmental Impact Assessment Report
26 Notification Of National Environment Board No.3, B.E.2535 (1992): The Criteria And Method Of Appointment Specialist Committee Member In Considering An Environmental Impact Assessment Report
27 Notification Of National Environment Board No.14, B.E.2540 (1997): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Environmental Impact Assessment Report
28 Notification Of National Environment Board No.34, B.E.2552 (2009): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Environmental Impact Assessment Report
29 Notification Of National Environment Board No.35, B.E.2552 (2009): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Environmental Impact Assessment Report
30 Notification Of National Environment Board No.38, B.E.2553 (2010): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Environmental Impact Assessment Report
31 Notification Of National Environment Board No.39, B.E.2553 (2010): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Initial Environmental Examination Report And Environmental Impact Assessment Report In Environmental Protection Zones
32 Notification Of National Environment Board No.40, B.E.2554 (2011): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Environmental Impact Assessment Report
33 Notification Of National Environment Board No.41, B.E.2554 (2011): The Criteria And Method Of Appointment Specialist Committee Member In Considering Of Initial Environmental Examination Report And Environmental Impact Assessment Report In Environmental Protection Zones
34 Notification Of Ministry Of Natural Resources And Environment: Time Duration In According To Notification Of The Ministry Of Natural Resources And Environment In Criteria, Method, Procedure And Guidelines For Preparation Of Environmental Impact Assessment Report For The Project Or Activity That May Affect Community Severely Both In The Quality Of Environment, Natural Resources And Health
Forms
No. List of Forms Forms
1 The report of showing the significant environmental effect, the protecting and amending measure of environmental effect and the measure of monitoring and inspecting the environmental effect (the form of Sor Phor Ror 1)
2 The front cover and the inside front cover of the analysing report of environmental effect (the form of Sor Phor Ror 2)
3 The certificate on creation of the environmental impact assessment report (the form of Sor Phor Ror 3)
4 The account name list of organizer of the environmental effect report (the form of Sor Phor Ror 5)
5 The form of showing the detail for presenting the analysis report of environmental effect (the form of Sor Por Ror 6)
6 The front cover and the inside front cover of the report of primary environmental effect (the form of Sor Phor 7)
7 The certificate on creation of the report (the form of Sor Phor 8)
8 The account name list of organizer of the primary environmental effect report (the form of Sor Phor 9)
9 Copy of the permit of being eligible person to create the environmental impact assessment report